Delivered2025

Construction of greenhouses in Surkhandarya, Bukhara and Namangan regions, financed by the International Bank for Reconstruction and Development (IBRD) and the International Development Association (IDA).

FinancingIBRD and IDA (World Bank Group)
LocationSurkhandarya, Bukhara and Namangan regions
Started30.04.2025
Completed05.09.2025
Construction of greenhouses in three regions
LocationSurkhandarya, Bukhara and Namangan regions, Uzbekistan
DirectionGreenhouse complexes
ScopeConstruction of greenhouses
Area0.9 ha
FinancingIBRD · IDA
Timeline30.04.2025 — 05.09.2025
01Result

Three sites in three regions, built and handed over under one internationally financed programme.

0.8 haUnder cover

Total area across all sites

3Regions

Surkhandarya, Bukhara, Namangan

116 daysStart to completion

30 April — 5 September 2025

IBRD · IDAFinancing

World Bank Group institutions

02Site record

3 Photographs · 2025
Greenhouse arch frame during construction
Tunnel greenhouses across rolling fields
Ripe strawberries on gutter
Next project

Well drilling and drip irrigation, 50 ha

50 ha · wells and drip network

Drip tubing along planted rows
Similar task?

Send us the site and the numbers you already have.

We will come back with a survey plan, an indicative budget range and the delivery model that fits the financing you are working with.

Engineers reviewing a structure