Delivered2024

Twelve pumping stations, 41 km of main canal lining and a supervisory control layer, delivered as a single turnkey contract for a regional water administration in Karakalpakstan.

ClientRegional water administration
RoleEPC — design, supply, install
Duration19 months
ContractTurnkey, single responsibility
Rehabilitation of a regional irrigation network
LocationKarakalpakstan, Uzbekistan
DirectionWater supply & irrigation
Scope12 pumping stations · 41 km canal lining · SCADA
Capacity3 200 m³/h combined
Command area11 400 ha
StandardsO‘zDSt / ISO 9001 · IEC 61439-2
HandoverQ3 2024, with a 24-month warranty
01Brief

Pumping equipment installed in the late 1980s was running far outside its efficiency envelope, unlined canal sections leaked into the substrate, and the administration had no measured picture of where the losses occurred. Any repair programme without instrumentation would have been guesswork.

Nima Xizmat was engaged to survey the whole network, design the rehabilitation, supply and install the equipment, and hand over a system the client’s own operators could run — with a single contract holding all of it together.

Excavator on soil
Surveyor with GNSS rod on site
Field survey · 2022

Six weeks of flow measurement and condition survey along the main canal preceded any design decision.

02Scope

01

Survey and hydraulic model

Flow, head and condition survey of 41 km of canal and 12 station sites; a calibrated hydraulic model used to size every replacement.

02

Pumping stations

Twelve stations re-equipped with new pump sets, soft starters, switchgear and instrumentation; existing civil structures retained and repaired.

03

Canal lining

18.6 km of the highest-loss sections lined; inlet and outlet nodes rebuilt with measuring flumes.

04

Control and telemetry

Station-level PLCs, radio telemetry back to a dispatch room, and a SCADA layer with a per-station water balance.

05

Commissioning and training

Wet commissioning of every station, and a four-week operator programme with written procedures in Uzbek and Russian.

06

Warranty and service

A 24-month warranty with a spares package and quarterly scheduled service visits.

03Result

Figures below are taken from the client’s own dispatch records for the 2025 irrigation season, twelve months after handover.

−29%Conveyance losses

From 29.4% to 20.3% of intake volume

+2 235 haReliably irrigated

Tail-end sections now served through the full season

−20%Energy per m³

Pump sets operating inside their efficiency band

0Unplanned stoppages

Across the first full season after handover

04Site record

6 Photographs · 2024
Aerial straight canal through fields
Pivot span at sunset
Excavator loading dump truck on earthworks
Aerial crop fields road and canal
Site worker cutting steel
Irrigation line along a farm track
05Equipment

Vertical turbine pump sets12 units · 180—420 KWEuropean manufacture, supplied new
Motor control centres12 assemblies · IEC 61439-2Assembled and type-tested before shipment
Flow measurement26 points · ElectromagneticCalibrated on site against a reference meter
Station PLCs and telemetry12 nodes · Licensed radioRedundant link back to the dispatch room
SCADA and reporting1 dispatch workstationWater balance per station, per day
Next project

Greenhouse complex, phase I

4.2 ha glass · climate automation

Aerial fields with long greenhouses
Similar task?

Send us the site and the numbers you already have.

We will come back with a survey plan, an indicative budget range and the delivery model that fits the financing you are working with.